Khan Resources to build power line, retention pond at Dornod site |
|
|
|
|
Friday, 19 September 2008 |
|
Khan Resources Inc. (CA:KRI:)
announced Thursday that it will build a power line and sedimentation
pond at its Dornod Uranium Project.
The electric power line will
be constructed from the Xin Xin Mine to the Dornod Uranium Property,
a distance of about 26 kilometers and an electrical substation will
also be built at the site. The Xin Xin Mine is connected to an electric
power line from the Choilbalsan generating plant, approximately 120
kilometers to the south.
Along with the contract for
the power line, an agreement for the supply of up to 15 MW of electricity
has been entered into with the Choilbalsan generating plant. The availability
of electrical power from this plant will eliminate the use of diesel
powered generators at the site and provide sufficient electricity for
the planned drainage and rehabilitation of the underground mine workings
in the spring of 2009.